You have just been promoted to the role of assistant project manager to Jack Welch, who is in charge of project DELTA

Week 3 Written Assignment – Homework Problem

Read the problem below and answer the two questions in a memo to management.  Be sure to include all supporting documentation with your answer. Carefully read the instructions at the end of the problem.

Project DELTA

You have just been promoted to the role of assistant project manager to Jack Welch, who is in charge of project DELTA. DELTA is a code name that he assigned to the development of a top secret handheld electronic medical reference guide. DELTA would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations.

Jack and his top notch project team were developing a project plan aimed at producing 30 working models in time for one of the biggest medical equipment trade shows, FutureMed.  The trade show will start on October 25.  Meeting the FutureMed October 25 deadline is critical to success.  All the major medical equipment manufacturers demonstrate and take orders for new products at FutureMed.  Jack also heard rumors that competitors were considering developing a similar product, and he knew that being first to market would have a significant sales advantage.  Besides, top management made funding contingent upon developing a workable plan for meeting the FutureMed deadline.

The project team spent the morning working on the schedule for DELTA.  They started with a WBS and developed the information for a network, adding activities they needed.  Then, the team added the time estimates they had collected for each activity.  Below is the preliminary information for activities with duration times and predecessors.

Activity Description Duration
(in days)

Predecessors
1 Architectural decisions 10 None
2 Internal specifications 20 1
3 External specifications 18 1
4 Feature specifications 15 1
5 Voice recognition 15 2,3
6 Case 4 2,3
7 Screen 2 2,3
8 Speaker output jacks 2 2,3
9 Tape mechanism 2 2,3
10 Database 40 4
11 Microphone/soundcard 5 4
12 Pager 4 4
13 Barcode reader 3 4
14 Alarm clock 4 4
15 Computer I/O 5 4
16 Review design 10 5,6,7,8,9,10,11,12,13,14,15
17 Price components 5 5,6,7,8,9,10,11,12,13,14,15
18 Integration 15 16,17
19 Document design 35 16
20 Procure prototype components 20 18
21 Assemble prototypes 10 20
22 Lab test prototypes 20 21
23 Field test prototypes 20 19,22
24 Adjust design 20 23
25 Order stock parts 15 24
26 Order custom parts 2 24
27 Assemble first production unit 10 25,26
28 Test unit 10 27
29 Produce 30 units 15 28
30 Train sales representatives 10 29

 

Instructions

Prepare a short memo to senior management that addresses the following questions:

  1. Will the project as planned meet the October 25th deadline?  Assume that the project start date is January 1st.
  2. What activities lie on the critical path? List all of them in correct sequence.

Attach supporting documentation that shows how you arrived at your answers.

Be sure to use tools you have learned about it Chapter 6, such as an AON network or Gantt chart. If you know how to use Microsoft Project, you may use it to validate your work. When creating an AON network, use the Automated Warehouse Order Picking Example in your book and the resulting AON network in Figure 6.8 on Page 173 as guide.

 

MICROSOFT WORD, APA FORMAT, SCHOLARLY REVIEWED CITATIONS

 